NEWSROOM   WHO WE ARE   MISSIONS   HISTORY
HOME

Public Affairs - News Release



Smith Point: Construction of Beneficial Use Sites   

     Construction is ongoing in Trinity Bay on three Beneficial Use Sites (BUS) that will eventually contain dredge material from the upcoming maintenance dredging of the Channel to Smith Point. Smith Point is located along the eastern shore of Trinity Bay south of Anahuac, Texas. The channel is a portion of the Channel to Liberty, the only portion currently sustaining commercial traffic. There are oyster production facilities at Smith Point that employ between 200 to 300 people. In FY02 Galveston District received a Congressional Add to restore project depth in the channel to allow the oystermen access to the facility. 

     After receiving the request, a Public Workshop was held to determine local needs. A channel survey disclosed that approximately 750,000 cy of material would need to be removed to restore the authorized channel dimensions, 9 feet deep by 150 feet wide. There were no available placement areas, so coordination began between the COE, the Chambers-Liberty Counties Navigation District (local sponsor), local oystermen, the USFWS, TPWD, Audubon Society, and Galveston Bay Foundation. After much discussion and coordination, a plan was developed to use the material 100% beneficially. The plan called for development of Beneficial Use Sites (BUS) 1-3, into which the dredge material would be placed. 

     BUS1 is Smith Point Island - an area frequented by several species of birds. Dredge material will be used here to increase the size of this island. The first order of business was to construct a stone breakwater to the north of the island to stop the island from eroding and to contain the dredge material behind it. The breakwater is approximately 2,300 feet long, with a 5-feet wide cap, and built to an approximate elevation of +1.5 to +2 MLT. The breakwater will also prevent dredge material from smothering nearby oyster reefs. Good coarse-grained material and shell hash will be pumped from the adjacent channel and used to good benefit in this location. 

     There is a lot of oyster and shell in the channel toward the eastern tip of Smith Point Island. This shell will be pumped to an area in the open bay, and to the north of the island. The shell will be placed so as to encourage oysters to attach and create a new oyster reef. 

     BUS2 is a 138-acre marsh creation site located just north of Robbins Memorial Park and the Channel to Smith Point. Approximately 8,500 linear feet of geotubes will be placed to form the U-shaped perimeter of the marsh. The geotubes will be placed to varying elevations (+3-3.5 feet) with periodic "circulation" tubes that will be collapsed to a lower elevation in the future to allow water to circulate through the marsh. Bertucci Corporation is the subcontractor currently placing the geotubes. They are filling the tubes with varying material from the adjacent bay bottom and from "borrow ditches" within the marsh. Approximately 650,000 cy of fine-grained dredge material from the adjacent channel will be placed inside the area defined by the geotubes to varying elevations within the marsh. 

     Once dredging is complete, marsh grasses such as spartina alterniflora will be planted to ensure vegetative cover by the end of the second growing season. The circulation tubes will then be collapsed allowing tidal penetration into the dredged material will be used beneficially. Construction of a beneficial uses site of approximately 357 acres, will replace the portion of the Shoal Point dredged material placement area that would be utilized for the development. 

 




Need More Information?
Updated: June 20, 2003