REGULATORY GUIDANCE LETTER
No. 01-1 Date: 31 October 2001
SUBJECT: Guidance for the Establishment
and Maintenance of Compensatory Mitigation Projects Under the Corps Regulatory
Program Pursuant to Section 404(a) of the Clean Water Act and Section 10 of the
Rivers and Harbors Act of 1899
1. 1. Purpose and applicability
a. a. Purpose.
Corps permits issued
under Section 404(a) of the Clean Water Act or Section 10 of the Rivers and
Harbors Act of 1899 routinely contain conditions that relate to compensatory
mitigation for resources that are going to be adversely affected or lost as a
result of a permitted activity. The
Corps is strongly committed to protection of the overall aquatic environment on
a watershed basis, including fully mitigating authorized impacts to all aquatic
resources, including wetlands. As
discussed in the National Research Council (NRC) report, Compensating for
Wetland Losses Under the Clean Water Act, (June, 2001), the Corps must
increase the effectiveness and compliance of mitigation required for authorized
impacts to the aquatic environment, including wetlands. This guidance letter provides direction
concerning factors that affect compensatory mitigation success in a variety of
contexts. This guidance adopts
definitions that were developed for use in accounting for the types of
mitigation used in Federal efforts to meet the national no overall net loss
policy and to account for projects designed solely to increase the
nation’s wetland base. These terms
were published on the U.S. Fish and Wildlife Service web page in July 2000, for
use in reporting gains and losses by Federal resource management agencies.
The guidance
also adopts the use of the terms “credit” and
“debit”. Acres have
traditionally been used as the standard measure in discussions of compensatory
mitigation as it relates to the national no overall net loss policy. This is primarily due to the difficulty in
finding one standard for quantifying the different functional components
considered during the evaluation of the ecological and physical parameters
required for decision-making. The use of
an accounting system based on credits and debits allows the program to
demonstrate comparability of the mitigation being required for authorized
impacts. The terms may change as methods
and techniques evolve to better describe the relationship between an adverse
effect and the compensatory mitigation required to offset or reduce that
adverse effect. Nevertheless, the
concepts embodied in the guidance below are intended to fully support the
national no overall net loss policy for wetlands and to provide a basis for
formulating decisions that will more effectively and fully mitigate impacts to
other aquatic resources, such as flowing streams.
b. b. Applicability.
This guidance applies to compensatory mitigation proposals submitted for
approval on or after the effective date of this guidance and to those in the
early stages of planning or development.
These policies are not retroactive for mitigation projects that have already
received approval.
2. 2. General Considerations.
All mitigation
required by the Corps should be based on a consideration of regional aquatic
resource requirements. Districts should
take an ecosystem approach to the formulation of compensatory mitigation
projects considering the resource needs of immediate and nearby
watersheds. Mitigation that includes a
mix of habitats such as open water (e.g., streams) as well as wetlands and
adjacent uplands is normally more ecologically sustainable.
a. a. Debit/Credit
assessment. The evaluation of
adverse effects should be undertaken with a view toward being able to assign an
identified debit to be offset by a credit.
The method for assessing debits should be comparable to the method used
for assigning credits. Corps regulatory
program project managers are responsible for using district-approved methods
(e.g., the Hydrogeomorphic Approach or acre-for-acre ratios) for assessing and
assigning credits or debits in terms of amount, type and location. The definitions for “debit” and
“credit” are provided (see attached definitions document).
b. b. Role of preservation.
Credit may be given when existing wetlands and/or other aquatic
resources are preserved (protected/maintained) in conjunction with
establishment, restoration, rehabilitation, and enhancement activities and when
it is demonstrated that the preservation will augment the functions of the
established, restored, rehabilitated or enhanced aquatic resource. Such augmentation may be reflected in the
amount of credit attributed to the entire mitigation project. In addition, the permanent preservation of
existing wetlands and/or other aquatic resources may be authorized as the sole
basis for generating credits in mitigation projects. In either case, consideration must be given to
whether wetlands and/or other aquatic resources proposed for preservation
perform physical, chemical and/or biological functions, the preservation of
which is important to the region in which the mitigation site will be located. Aquatic areas, including wetlands, that are
preserved as mitigation should also be under some documented level of threat
for development, which is the case for most privately held wetlands or other
aquatic areas.
c. c. Inclusion of upland areas.
Credit may be given for the inclusion of upland areas occurring within a
compensatory mitigation project to the degree that the protection and
management of such upland areas is an enhancement of aquatic functions and
increases the overall ecological functioning of the mitigation project (e.g.,
vegetated buffers or a mix of habitats).
d. d. Vegetated buffers.
Compensatory mitigation plans for projects in or near streams or other
open waters should normally include a requirement for the establishment and
maintenance of vegetated buffers next to open waters on the project site. In many cases, vegetated buffers will be the
only compensatory mitigation required and may be wetland, upland or a composite
mix of the two. Vegetated buffers should
normally consist of native species. The
width of the vegetated buffers should be determined based on documented water
quality or aquatic habitat loss concerns.
Vegetated buffers need not be required to be as wide as some technical
literature would suggest since the literature addresses the pre-human
colonization of North America. Normally,
vegetated buffers will be 50 feet wide or less on each side of a stream or
other open water area. All vegetated
buffers should be designed to provide water quality or aquatic habitat
functions (e.g., shading, habitat for animals that require aquatic and adjacent
upland areas as habitat) and ecological value.
e. e. Use of in-kind vs. out-of-kind
mitigation. In the interest of achieving functional
replacement, in-kind compensation of aquatic resource impacts will often be
appropriate. However, because
compensatory mitigation decisions should take into account the functions of the
aquatic environment, including wetlands, within both the landscape mosaic as
well as a watershed context, out-of-kind compensation may also be
appropriate. Out-of-kind compensation
should be practicable and environmentally equal or preferable to in-kind
compensation (i.e., of equal or greater ecological value to a particular
region). However, non-tidal aquatic
areas including wetlands should typically not be used to compensate for the
loss or degradation of tidal aquatic areas including wetlands, nor should the
reverse be true. Decisions to require or
allow out-of-kind mitigation are made on a case-by-case basis during the permit
evaluation process and should also consider the location (e.g., surrounding
land uses). Such decisions are usually
based on the amount of debits assigned to the impact site in comparison to the
credits assigned to the compensatory action (e.g., loss of a degraded site
associated with the restoration of a particularly vulnerable or valuable
aquatic habitat type).
f. f.
Mitigation ratios.
The Corps regulatory program allows for the use of ratios in determining
the amount of compensation required when there is a difference between the kind
of aquatic resource being impacted and the kind of mitigation being
required. Ratios must be based on an
identifiable rationale (e.g., use of an assessment methodology, rationale based
on a regional aquatic resource context, or a case-by-case rationale briefly
described in the decision document).
Other factors affecting mitigation ratios include temporal losses
between the time of impact and the time the mitigation site achieves a fully
functional level and the likelihood of mitigation success. All use of ratios should be to ensure that
the underlying policy of offsetting the authorized impacts will occur.
g. g. Types of compensatory mitigation. The types of mitigation projects used in
compensating for the loss of aquatic resources including wetland impacts are
listed below. A definition for each type
of compensatory mitigation project is provided in the attached definitions
document. The current view is that
restoration efforts provide the best potential for success in terms of
providing functional compensation; however, each type of mitigation has utility
and may be used as compensatory mitigation.
When assigning credit for a particular type or mix of mitigation types
within a mitigation project, the credit for the entire mitigation project
should be compared to the debit(s) formulated for the impact(s) being
authorized.
1. 1. Establishment
2. 2. Restoration (includes re-establishment
and rehabilitation)
3. 3. Enhancement
4. 4. Protection/Maintenance.
h. h. Timing of mitigation construction.
Financial and ecological considerations play important roles in
mitigation project development. It is
generally appropriate, in cases where there is adequate financial assurance
and/or where the likelihood of success of the project is high, to allow an
impact to occur before the mitigation plan is implemented. In this regard, the following minimum
requirements should normally be satisfied prior to any construction in aquatic
areas under an issued permit: (1) the
mitigation plans have been approved; (2) the mitigation project site has been
secured; (3) a permanent source of adequate water is available; and (4) the
appropriate financial assurances have been established. In addition, initial physical and biological
improvements should typically be completed no later than the first full growing
season following impacts to the aquatic environment by issuance of a
permit. If that is not practicable, then
additional compensatory mitigation or other measures that reduce the risk of
failure should be considered as part of the mitigation plan (e.g., use of a
higher mitigation ratio or increased financial assurance). For compensatory mitigation involving
in-lieu-fee arrangements or mitigation banking agreements, the guidance
applicable to those forms of mitigation must be followed. After-the-fact mitigation may be required
where permits are issued in response to emergencies or to resolve an
enforcement action. If a mitigation
project is implemented and documented to be successful before the impacts occur
from an authorized project, the mitigation ratio necessary to offset the
authorized impacts could be reduced, because there would be no temporal loss or
risk for the success of the mitigation.
i. i.
Watershed/holistic
approach for mitigation. Increasingly, the Corps is taking a watershed
approach in the regulatory program.
Mitigation projects are most successful if a holistic approach is taken
where a variety of aquatic resource types are protected in a mitigation project
(whether mitigation bank, in-lieu fee, or project-specific mitigation),
including open water, wetland and upland mixes.
Where such mix of ecological factors is included in the mitigation, all
of those features (open water, wetland, and upland resources which add to the
aquatic functions) should be included in the “credits” established.
3. 3. Compensatory mitigation project
development
a. a. Compensatory mitigation plans.
The compensatory mitigation plan should describe in detail the physical,
biological and legal characteristics of the project, and how the project will
be established and operated.
Compensatory mitigation proposals submitted with permit applications or
nationwide permit pre-construction notices may be either conceptual or detailed
depending on how much mitigation credit is needed to ensure the project has
minimal impact to the aquatic resource and depending on the reliability of the
parties implementing the mitigation to successfully follow through on the effort. However, careful consideration of each
component should ensure consistency and enforceability of mitigation plans.
At a minimum,
the components listed below should be considered and included in the mitigation
plan and/or special permit conditions. A
definition for each component is provided in the attached definitions document.
1. 1. Baseline Information;
2. 2. Goals of the Mitigation;
3. 3. Mitigation Work Plan;
4. 4. Success Criteria;
5. 5. Monitoring Plan;
6. 6. Contingency Plan;
7. 7. Site Protection;
8. 8. Financial Assurances;
9. 9. Responsible party for long-term maintenance.
b. b. Siting compensatory mitigation projects.
The selection of a site for a compensatory mitigation project requires
consideration of numerous factors including, but not limited to, the following:
1. 1. Geographic location. A
mitigation project should generally be located within the area (e.g.,
watershed, county) where a project can reasonably be expected to provide
appropriate compensation for the impacts to aquatic resources, including
wetlands, under consideration.
Mitigation in nearby watersheds may be appropriate and the rationale for
this determination should be provided in the mitigation plans. The further removed geographically from the
authorized impact the mitigation site is located, the more care must be taken
to ensure that the mitigation will reasonably offset the authorized
impacts. Ratios should generally
increase as the distance between the impact and mitigation sites increase.
2. 2. Air traffic.
Compensatory mitigation projects that have the potential to attract
waterfowl and other bird species that might pose a threat to aircraft should
not be sited within the limits specified by the Federal Aviation Administration
Advisory Circular on Hazardous Wildlife Attracts on or near Airports (AC
No: 150/5200-33, 5/1/97) currently 10,000 feet from the airport and 5 statue
miles if the attractant may cause hazardous wildlife movement into or across
the approach or departure airspace.
c. c. Use of off-site compensatory mitigation
vs. on-site compensatory mitigation. The Corps will carefully consider the use of
off-site mitigation, particularly for habitat mitigation such as many wetland
mitigation projects. This is
particularly important when there is no practicable opportunity for on-site
compensation, or when use of an off-site mitigation project is environmentally
preferable to on-site mitigation. The
2001 NRC report on mitigation in the Corps Regulatory Program found that
on-site mitigation may not be appropriate because of hydrologic alterations and
development on-site which could compromise the quality of the mitigation. On-site mitigation is appropriate for vegetated
buffers adjacent to open waters and water quality features such as storm water
ponds.
d. d. Agency roles and coordination.
The Corps will often choose to coordinate proposed mitigation plans with
the Environmental Protection Agency, the U.S. Fish & Wildlife Service, the
National Marine Fisheries Service, and/or the Natural Resources Conservation
Service for technical adequacy. In
addition, it is appropriate for representatives from tribal, state, and local
regulatory and resource agencies to participate where an agency has authorities
and/or mandates directly affecting or affected by the establishment, use or
operation of a project. The opportunity
for interagency review of the mitigation plan should be commensurate with the
form of authorization being contemplated and the scope of the mitigation
requirement (e.g., most nationwide permit compensatory mitigation plans only
require review by the Corps). In all cases, however, the Corps will determine the
amount and type of compensatory mitigation required by the permit to offset the
impacts to be authorized, taking into consideration the other agencies’
comments. Tribal, state and local rules
and/or laws may independently require more or less mitigation than the Corps
requires, but those rules or laws have no legally binding effect on the Corps
(unless incorporated as a condition of a Section 401 water quality
certification or comparable legal document)
e. e. Public review and comment. The
public should be notified of, and have an opportunity to comment on, all
proposed mitigation bank or in-lieu-fee arrangements during the development
process. Compensatory mitigation
projects associated with standard permit applications should be made available
for public comment to the extent practicable within the evaluation process
(i.e., if the applicant provides a mitigation plan with the application it
should be included in the public notice).
However, a mitigation plan is not required for issuance of a public
notice. If the mitigation plan is
detailed, a synopsis may be included in the public notice and detailed plans
made available for inspection at the office.
For forms of authorization other than standard permits, the opportunity
to comment should be based on the scope and potential for impacts to the
aquatic resource.
f. f.
Role of the permit
applicant. Permit applicants may propose the use of mitigation banks,
in-lieu fee arrangements, or separate activity-specific compensatory mitigation
projects. For individual permits, the
Corps will accept the applicant’s proposed mitigation if the Corps
determines that the proposed mitigation is appropriate and sufficient (i.e., in
or reasonably close to the impact area watershed and sufficient to offset the
impacts on a functional basis). For
regional general permits associated with Special Area Management Plans or other
watershed planning tools, the Corps can identify specific mitigation
requirements (e.g., mitigation bank or in lieu fee arrangement). This approach allows the Corps to take a
watershed approach in regulating and mitigating impacts.
g. g. Party responsible for compensatory
mitigation project success. All permits that require compensatory
mitigation will contain a provision that specifies the party responsible for
planning, accomplishing and maintaining the mitigation project. The Corps, in accordance with the success
criteria established for the project, will make the determination of project
success.
4. 4. Management of compensatory mitigation project sites.
a. a. Management and protection.
1. 1. Real estate interests.
The wetlands, uplands and/or other aquatic resources in a mitigation
project should be permanently protected with appropriate real estate
instruments (e.g., conservation easements, deed restrictions, transfer of title
to Federal or state resource agencies or non-profit conservation
organizations). The Corps may require
third party monitoring if necessary to insure permanent protection. In no case will the real estate provisions
require a signature by a Corps official.
Also, the Corps cannot hold deed restrictions on any property. The real estate provisions will not commit the
Corps to any interest in the property in question, unless proper statutory authority
is identified that authorizes such an arrangement.
2. 2. Funding.
The permittee or party responsible for accomplishing and maintaining the
mitigation project, including contingency funds for adaptive management, is
responsible for securing adequate funds to accomplish those responsibilities
associated not only with the development and implementation of the project, but
also its long-term management and protection.
3. 3. Enforcement.
All mitigation required by Corps permits is permanent unless otherwise
noted in the permit document. The Corps
may take enforcement action even after the identified monitoring period has
ended.
b. b. Monitoring requirements.
The permittee or the party responsible for accomplishing and maintaining
the mitigation project is responsible for monitoring the mitigation project in
accordance with monitoring provisions identified in the project plan. Monitoring plans and the frequency of
reporting will be designed to allow the Corps to determine the level of success
and identify problems requiring remedial action. Monitoring will be required for an adequate
period of time, normally 5-10 years, to ensure success.
c. c. Remedial action.
The project plan should stipulate the general procedures for identifying
and implementing remedial measures on a mitigation project. The Corps will determine the need for
remediation.
5. 5. Duration.
This guidance remains effective unless revised or rescinded.
FOR THE
COMMANDER:
/signed/
Encl ROBERT
H. GRIFFIN
Brigadier General, U.S. Army
Director of Civil Works
1. 1. Baseline Information: The mitigation plan should include a written statement which defines the location, size, type, functions and amount of debit associated with the aquatic and other resources to be impacted and the amount of credit resulting from the mitigation project. This baseline information should include a description of the location of the proposed mitigation site in relation to the aquatic resource area to be impacted. Baseline information may include quantitative sampling data for both the proposed mitigation site and the project impact area. In addition, the size (e.g., acreage of wetlands, length and width of streams) and timing of the mitigation should be articulated clearly.
2. 2. Goals of the mitigation: The mitigation plan should include a written statement of environmental goals and objectives. The goals should discuss the aquatic resource type (e.g., Hydrogeomorphic (HGM) class of wetlands or Rosgen class for streams) and the functions of the aquatic resources anticipated to be impacted and to be developed at the mitigation site(s). For example, for tidal wetlands, mitigation may be designed to replace lost finfish and shellfish habitat, lost estuarine production, or lost water quality functions associated with tidal backwater flooding.
3. 3. Resource Comparison:
a. a. Credit. A unit of measure (e.g., functional capacity units in HGM) representing the gain of aquatic functions at a compensatory mitigation site; the measure of function is typically indexed to the number of acres of resources restored, established, enhanced, rehabilitated or protected/maintained as compensatory mitigation.
b. b. Debit. A unit of measure (e.g., functional capacity units in HGM) representing the loss of aquatic functions at an impact or project site; the measure of function is typically indexed to the number of acres lost or impact by issuance of the permit.
4. 4. Mitigation Work Plan: The mitigation work plan should include detailed written specifications and descriptions of the work to be performed, including, but not limited to:
a. a. Boundaries of proposed restoration, establishment, enhancement, rehabilitation or protected/maintained areas (e.g., maps and drawings);
b. b. Replacement ratios developed consistent with the known difficulty and risk of replacement. The risk of mitigation failure is greater where the source and frequency of hydrology are uncertain and/or where a greater plant diversity is required. Therefore, these mitigation projects may require a higher ratio than those aquatic systems with greater predictability;
c. c. Construction methods, timing and sequence;
d. d. Data indicating historic and existing hydrology, stream bottom and/or soil conditions;
e. e. Source of water supply and connections to existing waters and proximity to uplands. In some areas, a water budget may also be necessary;
f. f. Elevations of existing ground at mitigation site;
g. g. Plant materials and scheme for planting;
h. h. Methods and times of year for planting;
i. i. Plans for control of exotic vegetation;
j. j. Elevation(s) and slope(s) of the proposed mitigation area to ensure they conform with required elevation for target plant species. Survey data indicating final elevations of the area(s) to be planted should be provided prior to commencement of planting;
k. k. Erosion control measures to prevent upland erosion into site are indicated;
l. l. Stream or other open water geomorphology and features such as riffles and pools, bends, deflectors, etc.;
m. m. A plan outlining the short and long term management and maintenance of the mitigation site.
5. 5. Ecologically based success criteria: Written
criteria will be developed to measure success of the compensatory mitigation
and included in the permit. The success
criteria will be used to determine if the mitigation is in compliance with the
terms and conditions of the permit. The
criteria may set specific quantitative measurements that must be met (e.g., a
minimum duration of soil saturation based on groundwater well data, 80 percent
vegetative cover by target species by the end of the second growing
season). The criteria can also be based
on reference sites and should provide the flexibility necessary to allow, when
environmentally desirable, unanticipated changes (e.g., natural stream channel
adjustments or long-term drought conditions).
This flexibility is critical because mitigation projects do not benefit
from continuous requirements to replant target species that cannot survive in
the restored, established or enhanced aquatic area as designed. Changing plant species or the physical design
parameters should be undertaken early in the mitigation phase when remediation
is required. Criteria for the operation
of mitigation sites should be based on the following (the detail will depend on
the size and ecological importance of the mitigation area):
a. a. Consider the hydrogeomorphic and
ecological landscape and climate.
Because landscapes have natural patterns that provide for sustainable
levels of functions of individual aquatic areas including wetlands, permittees
should locate mitigation sites in the comparable hydrogeomorphic class and/or
the appropriate landscape setting. Sites
with nearby wetlands will have natural recruitment sources for plants and
animals resulting in more overall sustainability.
b. b. Adopt a dynamic landscape
perspective. Mitigation site locations
should be made resilient to disturbances that occur in the surrounding
landscapes by, for example, preserving large buffers and connectivity to other
aquatic areas and tapping into surrounding natural processes and energies.
c. c. Restore or develop naturally variable
hydrological conditions. The hydrology
of naturally occurring wetlands and other aquatic areas often fluctuates in
water level, flow distribution, and frequency and this variability should
translate to mitigation sites.
Preferably, hydrology should be restored without reliance on human
intervention (e.g., pumping water) that requires continual maintenance.
d. d. Whenever possible, choose restoration
over establishment. Restoration
generally is more feasible and sustainable than establishment and has a greater
likelihood of success. Restoration includes
rehabilitation (e.g., removal of a chronic source of sediment to a stream with
an excessive bedload).
e. e. Avoid over-engineered structures. Mitigation projects should be designed to
require minimal long-term maintenance.
f. f.
Pay particular attention
to appropriate planting elevation, depth, soil type and seasonal timing and
depth, duration and timing of water delivery.
g. g. Provide appropriately heterogeneous topography. Microtopography and topographic variation are needed to promote appropriate hydroperiods that plants and animals depend on for survival. Use adjacent or nearby natural systems as models for aquatic elevations and flooding regimes. Require as-built survey data from sites where changes in topographic elevations are proposed as part of the mitigation plan.
h. h. Pay attention to subsurface conditions, including soil and sediment geochemistry and physics, soil compaction, groundwater quantity and quality, and infaunal communities. An understanding of soil permeability, texture and stratigraphy is needed before mitigation takes place. Also, the chemical structure of soils, surface water, groundwater and tides will affect the long-term outcome of a mitigation site. If practical, use the topsoil from the impacted wetlands for construction of the new wetland, as it will contain a hydrophytic vegetation seed bank.
i. i. Consider complications associated with wetland and other area establishment or restoration in seriously degraded or disturbed sites. Disturbances associated with degraded wetlands in developed areas (e.g., subdivisions) can result in the extensive invasion by exotic
species requiring active long-term management to support native species and maintain natural processes.
j. j. Require early monitoring as part of adaptive management. Mitigation should incorporate a monitoring program that provides early indications of problems such as exotic plant infestations integrated with an adaptive management process.
k. k. Take a holistic watershed approach when requiring mitigation. Typically, a mix of habitats, including not only wetlands, streams and other open waters but also uplands, should be considered.
6. 6. Contingency Plan: A contingency plan should be provided to allow for mid-course corrections, if necessary. A performance bond will be considered and implemented if appropriate.
7. 7. Site Protection: A written discussion of the means of protecting the mitigation area(s) will be developed and the permit conditioned accordingly. Methods include, but are not limited to, conservation easements, deed restrictions, preservation areas, etc. Generally, conservation easements held by state or local government, other Federal agencies such as the Fish and Wildlife Service, or non-governmental groups such as The Nature Conservancy or land trusts, are preferable to deed restrictions. Using homeowner’s associations as the grantee in a deed restriction or conservation easement or simply relying on rules that govern homeowner’s associations has had mixed results nationwide. Consequently, homeowner’s associations should be used for these purposes only in exception circumstances.
8. 8. Financial Assurances: Sufficient funds or other financial assurances need to be present to cover contingency actions in the event of default by the party responsible for mitigation success or failure to meet the success criteria. Accordingly, projects posing a greater risk of failure (e.g., no naturally occurring hydrology) should have comparatively higher financial sureties in place than those where the likelihood of success is more certain. This is especially important in situations where the impacts occur prior to construction and complete functioning of the mitigation site. Financial assurances may be in the form of performance bonds, irrevocable trusts, escrow accounts, casualty insurance, letters of credit, legislatively enacted dedicated funds for government operated banks or other approved instruments. Such assurances may be phased-out or reduced, once it has been demonstrated that the project is functionally mature and/or self-sustaining in accordance with success criteria.
9. 9. Mitigation Types: These are standard definitions for wetlands. Similar criteria and approaches should be used for streams and other open water areas.
a. a. Establishment: The manipulation of the physical, chemical, or biological characteristics present to develop a wetland on an upland or deepwater site, where a wetland did not previously exist. Establishment results in a gain in wetland acres.
b. b. Restoration: The manipulation of the physical, chemical, or biological characteristics of a site with the goal of returning natural/historic functions to a former or degraded wetland. For the purpose of tracking net gains in wetland acres, restoration is divided into:
1. 1. Re-establishment: The manipulation of the physical, chemical, or biological characteristics of a site with the goal of returning natural/historic functions to a former wetland. Re-establishment results in rebuilding a former wetland and results in a gain in wetland acres.
2. 2. Rehabilitation: The manipulation of the physical, chemical, or biological characteristics of a site with the goal of repairing natural/historic functions of a degraded wetland. Rehabilitation results in a gain in wetland function but does not result in a gain in wetland acres.
c. c. Enhancement: The manipulation of the physical, chemical, or biological characteristics of a wetland (undisturbed or degraded) site to heighten, intensify, or improve specific function(s) or to change the growth stage or composition of the vegetation present. Enhancement is undertaken for a specified purpose(s) such as water quality improvement, flood water retention, or wildlife habitat. Enhancement results in a change in wetland function(s) and can lead to a decline in other wetland functions, but does not result in a gain in wetland acres. This term includes activities commonly associated with enhancement, management, manipulation, and directed alteration.
d. d. Protection/Maintenance: The removal of a threat to, or preventing the decline of, wetland conditions by an action in or near a wetland. Includes purchase of land or easements, repairing water control structures or fences, or structural protection such as repairing a barrier island. This term also includes activities commonly associated with the term preservation. Protection/Maintenance does not result in a gain of wetland acres.