Planning and Environmental Documents for Public Review

Click here to view USACE Galveston District Planning and Environmental documents for public review.

Viewing & Comments

Viewing Notices: To view a full public notice or its associated drawings file (if any), click on either full public notice or permit drawings link in the attachments section. To download the file to your computer, right-click on the public notice or drawings link, then select "Save Target As" from the menu.

How to Send Comments on Regulatory Division Public Notices: Send comments to the Regulatory Division, U.S. Army Corps of Engineers, Galveston District, 2000 Fort Point Road, Galveston, Texas 77550 or by electronic mail to our Public Notice Comment Email. Comments made in reference to a public notice should include your name, address, phone number and the Department of the Army permit number referenced in the public notice (e.g. SWG-2015-00001).  

How to Send Comment on Other Galveston District Public Notices: Please follow the instructions included with the public notice. For Galveston District Planning and Environmental Documents for public review, please click here.

SWG-1994-02067 - West Gulf Marine, Inc. - Galveston County

Published Nov. 17, 2015
Expiration date: 12/18/2015

Full Public Notice    Project Plans

The applicant proposes to modify the permit to add mooring dolphins; to relocate existing structures and rip-rap; to dredge to a depth of 18 feet below mean low tide (MLT); to extend the time for maintenance dredging; and to install a concrete slab and bulkhead.

Specifically, the proposed components include the following activities:

 •             To dredge 100,000 cubic yards of material, to a depth of -18 feet MLT, by hydraulic means, within a previously authorized 6-acre dredge area

•             The dredge material will be pumped to Ryan Marine’s upland non-vegetated confined placement area

•             To place 171 cubic yards of clean fill material into 0.094 acre of waters of the U.S. for backfill during the installation of 560 linear feet of  bulkhead

•             To relocate clean rip-rap to uplands during the installation of bulkhead and replace rip-rap on the outside of wall of bulkhead after installation

•             To install a 12-inch concrete slab parallel to the bulkhead

•             To install 2 mooring dolphins

Equipment and materials associated with the proposed construction activities will be transported to the project site via truck and trailer, and/or barge and crane.